工程案例 – Shandong Hengli New Energy Engineering Co., Ltd //canyoncountyfestivaloftrees.com/en Fri, 14 Apr 2023 02:43:22 +0000 en-US hourly 1 //wordpress.org/?v=4.6.1 工程案例 – Shandong Hengli New Energy Engineering Co., Ltd //canyoncountyfestivaloftrees.com/en/cases/1785 //canyoncountyfestivaloftrees.com/en/cases/1785#respond Fri, 13 Jan 2023 09:17:15 +0000 //canyoncountyfestivaloftrees.com/?p=1785 Sorry, this entry is only available in 中文.

]]>
//canyoncountyfestivaloftrees.com/en/cases/1785/feed 0
工程案例 – Shandong Hengli New Energy Engineering Co., Ltd //canyoncountyfestivaloftrees.com/en/cases/1765 //canyoncountyfestivaloftrees.com/en/cases/1765#respond Tue, 27 Dec 2022 07:38:26 +0000 //canyoncountyfestivaloftrees.com/?p=1765 Sorry, this entry is only available in 中文.

]]>
//canyoncountyfestivaloftrees.com/en/cases/1765/feed 0
工程案例 – Shandong Hengli New Energy Engineering Co., Ltd //canyoncountyfestivaloftrees.com/en/cases/1236 //canyoncountyfestivaloftrees.com/en/cases/1236#respond Thu, 20 Aug 2020 01:40:54 +0000 //canyoncountyfestivaloftrees.com/?p=1236 Sorry, this entry is only available in 中文.

]]>
//canyoncountyfestivaloftrees.com/en/cases/1236/feed 0
工程案例 – Shandong Hengli New Energy Engineering Co., Ltd //canyoncountyfestivaloftrees.com/en/cases/1313 //canyoncountyfestivaloftrees.com/en/cases/1313#respond Sun, 22 Dec 2019 10:47:26 +0000 //canyoncountyfestivaloftrees.com/?p=1313 Sorry, this entry is only available in 中文.

]]>
//canyoncountyfestivaloftrees.com/en/cases/1313/feed 0
工程案例 – Shandong Hengli New Energy Engineering Co., Ltd //canyoncountyfestivaloftrees.com/en/cases/570 //canyoncountyfestivaloftrees.com/en/cases/570#respond Thu, 07 Dec 2017 02:38:41 +0000 //canyoncountyfestivaloftrees.com/?p=570 Sorry, this entry is only available in 中文.

]]>
//canyoncountyfestivaloftrees.com/en/cases/570/feed 0
工程案例 – Shandong Hengli New Energy Engineering Co., Ltd //canyoncountyfestivaloftrees.com/en/cases/300 //canyoncountyfestivaloftrees.com/en/cases/300#respond Tue, 21 Jun 2016 03:06:32 +0000 //canyoncountyfestivaloftrees.com/?p=300 Continue reading "Project: 5th stage dynamic technique improvement project of Luxi Chemical Group Co., Ltd"]]> 20150902

Project

5th stage dynamic technique improvement project of Luxi Chemical Group Co., Ltd

Constructing company

Luxi Chemical Group Co., Ltd

Equipping plan

two pulverized coal boilers of high temperature and high pressure at 680t/h and one B90MW back-pressure turbo generator

Working range

feasibility study, primary designing, working drawings and completing drawing designing.

Period of project

2014

]]>
//canyoncountyfestivaloftrees.com/en/cases/300/feed 0
工程案例 – Shandong Hengli New Energy Engineering Co., Ltd //canyoncountyfestivaloftrees.com/en/cases/153 //canyoncountyfestivaloftrees.com/en/cases/153#respond Mon, 09 May 2016 12:21:17 +0000 //canyoncountyfestivaloftrees.com/?p=153 Continue reading "City Grid reconstruction project of Huhehaote, Inner Mongolia Electricity Board"]]> 201605092001 201605092002

Project

City Grid reconstruction project of Huhehaote, Inner Mongolia Electricity Board

Constructing company

Huhehaote, Inner Mongolia Electricity Supply Co., Ltd

Equipping plan:

circuit route planning and put underground

Working range

primary drawings, working drawings and completing drawing designing

Period of project

2013

Project introduction

The project was finished in December 2013. 15-kilometer City Grid is designed. mainly involving 35kV and 10kV circuits and partial 110kV circuits, as an important project of city grid upgrade and reconstruction of Huhehaote Electricity Board

]]>
//canyoncountyfestivaloftrees.com/en/cases/153/feed 0
工程案例 – Shandong Hengli New Energy Engineering Co., Ltd //canyoncountyfestivaloftrees.com/en/cases/149 //canyoncountyfestivaloftrees.com/en/cases/149#respond Mon, 09 May 2016 12:18:57 +0000 //canyoncountyfestivaloftrees.com/?p=149 Continue reading "Secondary pressure-reducing reconstructing project of Ji Steel"]]> 201605091902 201605091901

Project

Secondary pressure-reducing reconstructing project of Ji Steel

Constructing company

Shan Steel Group

Equipping plan

110kV AIS transformer station converted to GIS one

Working range

working drawings and completing drawings

Period of project

2011

Project introduction

The project has been put into use since November 2011. The outdoor AIS transformer station of ji Steel was converted to an indoor GIS transformer station with 300-meter cable tunnel at the same time, as a pivotal project of secondary pressure-reducing upgrade and reconstruction and cables buried underground.

]]>